Female Track Worker in Steinway Tunnel
fall update Click here for update
on last weekend's work


Last spring, to improve the reliability and performance of the 7line icon line, we began critical maintenance and infrastructure work in the more than century-old Steinway Tunnel, which links Manhattan and Queens and began installing a new signal system known as Communications Based Train Control (CBTC).  While maintenance in the tunnel is ongoing, our accomplishments so far include:

  • installation of 8,000 track plates
  • cleaning of more than 9,600 feet of track
  • rewired track circuit and signals
  • serviced pump equipment and cleared drains
  • installed 8,000 feet of fiber optic cable
  • replaced switch, rail and power components
Substantial work remains, however, and this means continued 7line icon line service changes for several years. When completed, CBTC will result in more reliable service, more frequent service and countdown clocks. We realize this is an inconvenience and changes the way you travel, but the work is necessary for the modernization and improvement in the line’s reliability.

Planned Service Changes in 2012
Until April 2, 2012

  • All weekends from 12:01 AM Sat to 5 AM Monday, there will be no 7 line icon trains between Queensboro Plaza and Times Sq-42 St
February 25 – 27
March 3 - 5, 10 - 12, 17 - 19*, 24 - 26, Mar 31 - Apr 2
  • All times until April 2, 2012, 7 line icon trains skip Court Sq in both directions/No transfers between 7 line icon and G line icon trains at Court Sq. The station is closed to allow for the replacement of the platforms, windscreens, and installation of Americans with Disability Act (ADA) boarding areas.

  • Station Improvement work at Vernon Blvd-Jackson Av and Hunters Point Av will be performed. Work entails replacement of platform edge concrete, installing rubbing board, tactile platform edge ADA warning strips and repairing damaged platform areas, walls, track ceilings and improving station lighting.